To plan & deliver all transmission activities of 4x350MW TPP aligned with the targeted milestones to ensure timely completion of the transmission systems with safety & quality for evacuation of power within the cost & time line.
Preliminary Survey, Final Survey, Detailed Survey of the most feasible Route for 400KV Dedicated Line to PGCIL
Finding out the alternate solution to 220KV diversion Line by Heightening of line proposal.
Finding out the only feasible route for 400KV S/C line to OPTCL.
-Charging of 400KV LILO line for availing start-up power & interim power evacuation.
-Preparation of the erection and foundation completion check lists
-Carry out the Cube tests, cement, core & fine aggregate tests and maintaining the required test reports as per standard.
-Execution of each work with safety, quality & its measurement, billing in time.
-Planning & follow up of additional resources on regular basis for timely completion of work.
-Liasoning with OPTCL, PGCIL, RAILWAYS for approval of Power Line Crossing Proposals.
-Regular follow up with agency by reviewing on daily, weekly & monthly basis.
-Identifying critical areas & adopting the corrective measures to meet the schedule.
-Lead Time.
-Planned Vs. Actual.
-Within the Budget.
-Compliance & strict adherence to QAP, maintaining Protocols for the same.
-Non-compliance report.
-No. of accidents.
-Audit report.
External - Roles you need to interact with outside the organization to enable success in your day to day work
Internal - interaction with C and C, Stores regarding the bills and way bill issues.
Identifying New Capital Expenses- 400KV S/C line from GKEL to OPTCL, Meramandali Grid Sub-Station(Rs.25crores approx.)
-Charging of Circuit-1 of 400KV Talcher-Meramandali LILO line within the budget amount of Rs 48,015,270.
-Handling of Agencies like BSTL, Empowertrans Pvt. Ltd. for 400KV LILO,Diversion & Dedicated Line.
-Influence in the locality for uninterrupted site activities of ongoing 400KV Dedicated line to PGCIL, Angul & Proposed 400KV S/C line to OPTCL, Meramandali.
.Pre-University